The New School Building Project

In July 2022, Becket were chosen to be developed as part of the Department for Education's (DfE) School Rebuilding Programme (SRP).

This page will keep you up to date with information that we have about the project.

Architect Drawing

Here are some news articles about the project:

Derbyshire Live: Derby school could be totally demolished and rebuilt

BBC: Plans to rebuild and demolish primary school submitted

Here are some updates about the project, including some photos and videos from our drone:

05/12/2025

The "Topping Out Ceremony" didn't happen due to the severe wind warnings, however, lots of progress has been made!

  • Ground floor and first floor slabs complete;
  • Roof is water tight – they are adding insulation layers and parapet panels;
  • 1st floor corridor walls built for mechanical, electrical and sprinkler work to start on 8th December;
  • 1st floor windows installed will be installed week beginning 8th December;
  • Ground floor brick work to start on 15th December;
  • Retaining walls around MUGA and tarmac to be completed before Christmas

//www.youtube.com/embed/ene5EfGN6uA#t=0.5

 

//www.youtube.com/embed/5Xr3WyW-HuA#t=0.5

 

31/10/2025

They have done some more works on the drains and are nearly there with the roof - ready for the "Topping Out Ceremony".

 

//www.youtube.com/embed/ZrmmhpKKqQs#t=0.5

 

//www.youtube.com/embed/EA2RkkaLZJU#t=0.5

 

17/10/2025

They have started to construct the roof and floors.

 

//www.youtube.com/embed/wwr1xt2bZ2k#t=0.5

 

//www.youtube.com/embed/7139BSeZMpM#t=0.5

 

//www.youtube.com/embed/ea_wqPj83wc#t=0.5

 

06/10/2025

Finishing off the steel frame.

 

//www.youtube.com/embed/wpiwnei5aGU#t=0.5

 

//www.youtube.com/embed/WNdM0YTRX3o#t=0.5

 

30/09/2025

Mrs Guest and Mr Beattie took the School Council up to the site to sign one of the steels for the building.

 

 19/09/2025

 The steel structure has gone up very quickly!

 

//www.youtube.com/embed/l4ZATX-F7VI#t=0.5

 

//www.youtube.com/embed/P9-8kPiek-U#t=0.5

 

05/09/2025

A brief summary of the next activities:

  • Build retaining walls for the new car park
  • Begin constructing the steel frame 

 

//www.youtube.com/embed/PKo7B6uCWZg#t=0.5

 

 11/08/2025

 A brief summary of the next activities:

  • Continue with earthworks
  • Start preparing foundations for the steel frame
  • Install the lift shaft

 

//www.youtube.com/embed/CVwWdzzjAlU#t=0.5

  

14/07/2025

 A brief summary of the next activities:

  • Continue with earthworks, with multiple wagons taking rubble and materials offsite each day
  • The large excavation behind the fence is for the attenuation tank (designed to collect and store excess surface water run-off ) beneath the MUGA (Multi-Use Games Area)
  • Next big visible change will be when a crane arrives to install the lift shaft, hopefully in early August, and the steel frame starts to be built

 

//www.youtube.com/embed/v95ayBLFzLs#t=0.5

22/06/2025

A brief summary of the next activities:

  • Continue topsoil strip and cart off site
  • Continue to break up demolition waste and cart off site 

 

//www.youtube.com/embed/s0lmZhr3CUU#t=0.5